NIRD2020 status, March 2021
Published:
Wed, 31/03/2021 - 10:48
Author: Kjersti Strømme
Author: Kjersti Strømme
The procurement plan of the NIRD2020 project has been slightly modified due to the current pandemic. Our updated procurement plan is as follows:
Mid April 2021
Publishing tender documents
Mid Aug 2021
Reception of tenders
End sept 2021
Contract award
Mid Oct 2021
Signing of contract
Jan 2022
Site acceptance test