NIRD2020 status, March 2021

The procurement plan of the NIRD2020 project has been slightly modified due to the current pandemic. Our updated procurement plan is as follows:

Mid April 2021
Publishing tender documents
Mid Aug 2021
Reception of tenders
End sept 2021
Contract award
Mid Oct 2021
Signing of contract
Jan 2022
Site acceptance test

To the NIRD2020 Project page